TxDOT continues Wood County road projects this week

Posted 11/19/26

The Texas Department of Transportation has scheduled roadwork across Wood County for the week of Nov. 16, including continued construction on US 69 and resurfacing on FM 14.  

Crews are …

This item is available in full to subscribers.

Please log in to continue

Log in

TxDOT continues Wood County road projects this week

Posted

The Texas Department of Transportation has scheduled roadwork across Wood County for the week of Nov. 16, including continued construction on US 69 and resurfacing on FM 14. 

Crews are scheduled to overlay FM 14 between SH 37 and SH 154. Motorists should expect lane closures with flaggers directing traffic. Edge repairs are also planned at various locations throughout the county. 

Work continues on the $37.9 million US 69 overpass project near FM 779. Crews are scheduled to continue bridge construction and asphalt paving. Traffic has shifted onto temporary pavement south of the existing highway, with traffic detouring beneath the bridge during construction. 

The project extends from approximately one mile north to one mile south of FM 779 and includes a new overpass, drainage improvements, paving and roadway markings. Lamar Companies LLC is the contractor, with completion anticipated in November. 

On SH 37, crews are completing final details on a $4.1 million project to widen the roadway and install a continuous two-way left-turn lane between County Roads 2460 and 2320. Baker & Company Construction LLC is the contractor, with completion anticipated in March 2027. 

TxDOT reminds motorists to slow down and remain alert in construction zones. Work schedules are subject to change due to weather, equipment issues or other unforeseen conditions.